Nusa Dua Beach Hotel & Spa Revised Renovation Advice The management of the Nusa Dua Beach Hotel have sent a revised notice advising they will now be undergoing renovations until 31 December 2011. The renovations of the Nusa Dua Spa have been completed and the spa has reopened its doors. The works on the main swimming pool have been completed and it has been reopened. Upgrades of the Royal Residence are on-going and are scheduled for completion by December 2011. 1 June 2010 to 14 April 2011 Phase 1 - Nusa Dua Wing The major renovation of the Superior rooms will be finished January 2011. The hotel will undergo renovations to 82 rooms in the Nusa Dua Wing, during this time guests will be allocated rooms in the Agung Spa or Garden Wing. January 2011 - 31 December 2011 Phase 2 - Agung Spa Wing and Agung Garden Wing The reopening of the Nusa Dua Wing will be followed by the second phase of the refurbishment. The entire 162 rooms in the Agung Garden Wing will be closed from mid January until the end of July. This will be followed by works on the 137 rooms in the Agung Spa Wing which will be closed from August until 31 December 2011. During this time guests will be allocated rooms in the Nusa Wing. The hotel will also close the lobby bar in January 2011 to undertake roof repairs. Works will be carried out daily 9.00am to 6.00pm. The hotel has advised major noise will take place during the January and February 2011, however light noise/pollution may be experienced throughout the remainder of the construction period. The hotel will do all possible to minimise noise and ensure guest comfort. If your passengers wish to amend their accommodation, New Horizons Holidays will waiver any amendment fees. If you require any further information, please do not hesitate to contact our reservations department. NEW HORIZONS HOLIDAYS 12 December 2010